DON27BZ01-NV002 TITLE: Fire Resistant Joiner Bulkhead
COMPONENT TECHNOLOGY PRIORITY AREA(S): Advanced Materials;Sustainment
PROJECTED CMMC LEVEL REQUIREMENT: Level 2 (Self)
OBJECTIVE: Develop a material/system to increase the fire-resistance of joiner bulkheads on ships and compartment-level fire containment while meeting Navy requirements for weight, fit, cost, fire, smoke and toxicity.
DESCRIPTION: Fire represents a grave hazard to Navy vessels. Recent fire events have propagated through joiner bulkheads and resulted in significant fire damage, which poses a substantial threat to personnel and equipment. Uncontrolled fires can propagate throughout a ship and cause extensive damage to machinery, equipment, and ship compartments; additionally, fires represent an extreme risk to ship personnel. The Navy has made numerous improvements to make ships more fire-resistant but is seeking improvement for containment of compartment-level fire events seen in recent and historical ship fires (i.e., USS OSCAR AUSTIN, USS CONYNGHAM, USS STARK, and the cruise ship Star Princess). More fire-resistant joiner bulkheads would allow damage control teams to contain and extinguish fires more easily before they could grow to threaten the ship. Innovation is needed to meet Navy goals with regard to weight, cost, fit, and performance.
The Navy seeks an improved fire-resistant joiner bulkhead that would reduce the damage ships sustain during fires, as well as improve safety for the crew.
Development of a fire-resistant joiner bulkhead faces several technical challenges. First, any fire-resistant joiner bulkhead must not have a significant weight increase. Given the quantity of joiner bulkheads onboard ships, any weight increase could add significant weight to the ships, which will impair and degrade ship performance. Second, the improved joiner bulkheads must not excessively exceed the width of current joiner bulkheads. Destroyers have confined spaces and for the comfort and operational capability of the crew, any new joiner bulkhead cannot greatly exceed the dimensions of the existing panels. Third, any fire-resistant joiner bulkhead must be a cost-effective solution for the Navy. In particular, the fire-resistant joiner bulkhead must not substantially increase the costs to install at the shipyard. The reason for this concern is that joiner bulkheads sometimes require modification at the shipyards to fit the exact dimensions of the ship. Any solution that requires expensive edge treating or would otherwise be cost-prohibitive to modify at the shipyards will not be considered. Lastly, the improved joiner bulkhead must meet or exceed the requirements to be certified for shock and fire performance as AN-30 class per MIL-STD-3020 and pass Navy Fire, Smoke, Toxicity (FST) testing per MIL-STD-1623. This is a vital requirement to demonstrate that any new material in the joiner bulkhead will not release dangerous particulates as it burns or fails if there is an impact.
Research into fire-resistant materials has revealed several technology advances in the areas of intumescent coatings, coatings that incorporate nanomaterials to aid in thermal regulation, or advanced high-performance fibers; however, there is no current commercial solution available. The Navy is also open to bio-composites, bio-polymers, or other materials that have the potential to provide superior fire-resistance with reduced toxicity as compared to many commercially available products.
PHASE I: Develop a concept for a fire-resistant joiner bulkhead that meets the requirements above. Demonstrate the feasibility of the concept in meeting the Navy needs prescribed above and establish that the concept can be developed into a useful product for the Navy. Establish feasibility of a new fire-resistant material/system via small-scale testing. If the Phase I Option is exercised, include the initial design specifications and a capabilities description to build a prototype solution in Phase II.
PHASE II: Develop and deliver a prototype fire-resistant joiner bulkhead for evaluation. (Note: The prototype will be evaluated to determine capability in meeting the performance goals defined in the Phase II SOW.) Demonstrate product performance through prototype evaluation, modeling, and demonstration over the required range of parameters as defined by the Navy. Participate in an extended evaluation in a land-based test environment to refine the prototype into a design that will meet Navy requirements. Prepare a Phase II manufacturing and development plan, including drawings of connection details, to transition the improved fire-resistant joiner bulkhead to Navy use.
PHASE III DUAL USE APPLICATIONS: Support the Navy in transitioning the fire-resistant joiner bulkhead to Navy use. Develop installation and maintenance manuals for the improved fire-resistant joiner bulkhead to support transition to the Fleet.
Many potential commercial applications for improved fire-resistant joiner bulkheads exist; examples include commercial shipping, construction, aerospace, and automotive industries.
REFERENCES:
KEYWORDS: Fire Safety; Intumescent Coatings; Bio-Composites; Bulkhead Fire Containment; Fire Protection; High-performance Fibers
end of topic -->| 11/10/26 | Q. | Is the Navy’s main concern with fire resistance of the bulkhead due to a failure of the panel face or transmission at the edges and penetrations? |
| A. | Main concern is failure of the panel by any means allowing fire spread to adjacent compartments. Gap and penetrations can be mitigated through usage of other means (i.e. intumescents, insulation) that would constitute a system of materials to achieve goals. All aspects of system must be tested to ensure proper demonstration of the system. | |
| 11/10/26 | Q. | Does the Navy seek the development of an entirely new fire-resistant joiner bulkhead system that improves upon current state-of-the-art panel technology, or would the Navy also be receptive to a retrofit coating-based thermal protection system (TPS) applied to existing state-of-the-art joiner bulkhead panels? Specifically, would a coating-based TPS that enhances fire resistance and compartment-level thermal containment, while meeting applicable weight, smoke, toxicity, durability, and cost requirements, be considered a viable alternative to developing a new bulkhead system? |
| A. | Yes | |
| 11/9/26 | Q. | For Phase II AN-30 qualification under MIL-STD-3020, must shock and fire be demonstrated on the same prototype panel in one campaign, or may those qualifications be sequenced on separate panels of the same design? |
| A. | Yes they are to be demonstrated on the same panel. Test sequence would be to perform the MIL-STD-901 shock testing and then the fire testing. | |
| 11/9/26 | Q. | Beyond MIL-STD-1623 FST, are there prohibited constituents (for example specific halogenated flame retardants or VOC limits) that should constrain Phase I material selection? |
| A. | No | |
| 11/9/26 | Q. | For retrofit: is a coating or overlay applied to existing joiner faces acceptable if AN-30 and MIL-STD-1623 FST are met without full panel replacement, given the preference for a single new-construction-and-retrofit solution? |
| A. | There is no preference for any form of solution. Coatings, overlays, and other enhancements to existing joiner bulkhead material are equal solutions to full panel replacement. | |
| 11/2/26 | Q. | Must the Phase I concept already include the panel-to-structure attachment method (fastener pattern, edge finish) needed for shipyard modification, or may attachment details wait for Phase II while Phase I focuses on the material/system? |
| A. | Phase I is focused on feasibility, so detailed design such as attachment methods can wait until Phase II. | |
| 11/9/26 | Q. | For Phase I coupon testing (flame spread, smoke opacity, toxicity, cone calorimetry), what coupon size, thickness and orientation does the Navy prefer so results are comparable across proposers? |
| A. | Small scale testing is to be performed IAW MIL-STD-1623. Based upon the type of material submitted (i.e. insulation, panel covering, new panel) the tests will be selected utilizing MIL-STD-1623. Typical small scale tests are ASTM E-800, E-882, E-162, E-1354. Flame spread index – 6”x18”, Cone Calorimetry - 4”x4”, Smoke/Toxicity – 3”x3”. Cone calorimetry is conducted in a horizontal configuration, Smoke/toxicity is performed in a vertical orientation, flame spread is performed at an offset vertical angle of ~30deg. Typical thickness is ~0.25” however full thickness of ~5/8” is acceptable. | |
| 11/9/26 | Q. | Beyond the AN-30 fire exposure referenced in MIL-STD-3020, are there peak temperatures, heat flux levels or fire durations from recent shipboard fires that the Navy would like Phase I testing to address? |
| A. | Negative. We do not specify based upon fire events. The fire exposures in MIL-STD-3020 are the current “extremes” that the Navy tests all material to. | |
| 11/2/26 | Q. | For Phase I coupon testing, should specimens be prepared on the current joiner panel construction, or is a representative substrate (for example, steel or aluminum plate) acceptable for demonstrating material feasibility? |
| A. | The coupon should be representative of the proposed solution, whether that is an entirely new panel or the existing panel with enhancements. | |
| 11/9/26 | Q. | MIL-STD-3020 distinguishes restricted application (fire threat from one side) from unrestricted application (fire threat from either side). Should the improved joiner bulkhead be designed for restricted or unrestricted application? |
| A. | Restricted and unrestricted variants can be proposed as part of the project, but if only one variant is proposed it should provide unrestricted protection. | |
| 11/9/26 | Q. | As installed, is there an air gap, insulation, or other material between adjacent joiner panels or on either side of the bulkhead? Please describe a typical installed joiner bulkhead assembly, including panel joints and attachment to the deck and overhead. If available, a drawing, photo, or 3D schematic of a typical installation would be helpful. |
| A. | Details are in drawing 803-5959189. Joiner bulkhead panels are attached at the top and bottom with curtain plates and coaming and the seams between them are sealed or caulked. | |
| 11/7/26 | Q. | Can the Navy provide additional details regarding the construction of the current 5/8-inch joiner bulkhead used as the baseline for this topic, specifically:
1. Face-sheet material and nominal thickness. 2. Core material, density, and nominal thickness. 3. Bonding or manufacturing method. 4. Reference panel specification or representative commercial product. This information would help prospective offerors establish a technically meaningful baseline for evaluating alternative lightweight, fire-resistant sandwich-panel constructions. |
| A. | 1. Facing material is either phenolic resin impregnated fiberglass facing (nominal thickness 0.035 inches) or stainless steel AISI Type 304 (nominal thickness 0.025 inches).
2. Core material is aramid fiber honeycomb, 1/4 inch hexagonal in accordance with Mil. Spec. MIL-C-81986 except that the core density is 3 lb/ft3. Overall bulkhead thickness (including face sheets) is 0.625 inches 3. Blue 4. 803-5959189 |
|
| 11/6/26 | Q. | MIL-STD-3020, paragraph 6.5, describes AN-Class divisions as analogous to IMO A-Class divisions, which are non-combustible. Is a non-metallic or polymer composite joiner bulkhead eligible for AN-30 qualification under MIL-STD-3020 for this topic? |
| A. | Yes, provided they are non-combustible. | |
| 11/5/26 | Q. | This response you provided for a question submitted on October 19th: "Current joiner bulkheads do not have a fire-resistance classification. Current panels are approximately 5/8” in thick with an areal weight of 1.2 – 3.1 lbs. and the following mechanical properties (based on 4 ft. X 7 ft. Panel) 1. Edgewise compression yield @ 200 degrees F: 14,000 psi 2. Core shear @ 200 degrees F: 70 psi 3. Flatwise tension @ 200 degrees F: 150 psi 4. Beam flexture @ 200 degrees F: 14,000 psi" Is the aerial weight you listed (1.2-3.1 lbs,) correct with correct units. This looks wrong. Please clarify this. |
| A. | Thank you for catching the error. The correct areal weight should be 1.2 – 3.1 lbs / sq. ft. | |
| 11/3/26 | Q. | Does Phase I require coupon testing with exposed cut edges or penetrations? If so, please specify required configurations and acceptance criteria. |
| A. | Negative | |
| 11/3/26 | Q. | What test methods and standard revisions, pass/fail thresholds, and exposure or conditioning requirements apply to flame spread, smoke opacity, toxicity, and cone calorimetry? For toxicity, please specify required analytes and reporting basis. Please identify which, if any, of these requirements are proposer-defined for Phase I. |
| A. | Small scale testing is to be performed IAW MIL-STD-1623. Based upon the type of material submitted (i.e. insulation, panel covering, new panel) the tests will be selected utilizing MIL-STD-1623. | |
| 11/2/26 | Q. | ·Is the primary interest new construction, in-service repair and backfit, or both? |
| A. | The sponsoring program office is focused on new construction. However, the goal would be a solution that is applicable to in-service repair and retrofit as well. | |
| 11/2/26 | Q. | ·Can the Navy provide sample panels of the current joiner bulkhead design, or identify the baseline construction, for side-by-side comparison testing? |
| A. | The project is looking for AN-30 fire protection, not a measured improvement over what is on ships today. Details on existing joiner bulkheads have been provided for space and weight considerations, but space and weight are secondary considerations compared to fire protection. | |
| 11/2/26 | Q. | ·For Phase I feasibility, is small-scale coupon testing (e.g., cone calorimetry, smoke density, toxic gas screening) sufficient to address MIL-STD-1623 FST requirements? For shock, is analysis plus small-scale mechanical testing acceptable, or is a specific screening method preferred? |
| A. | Phase 1 should be small scale coupons only and will meet the 1623 FST requirements. Shock testing would be the medium to large scale shock testing due to full system/panels size. | |
| 11/2/26 | Q. | Q TEXT HERE ? |
| A. | A TEXT HERE | |
| 10/19/26 | Q. | Given that Phase I calls for small-scale feasibility testing, does the Navy expect testing specifically under MIL-STD-3020 conditions during Phase I, or would representative small-scale fire testing demonstrating a credible pathway toward AN-30 be acceptable?
Would it be appropriate to defer full-scale fire and shock qualification to Phase II while using Phase I to evaluate and compare several promising configurations? |
| A. | 1. During Phase I the focus is on material feasibility and will involve testing material coupons. Flame spread, smoke opacity, toxicity, cone calorimetry.
2. Full-scale fire and shock qualification is intended for Phase II. |
|
| 10/19/26 | Q. | Are there quantitative targets for maximum panel thickness, allowable weight increase and acceptable installed-cost increase relative to current joiner bulkheads?
Are there particular fabrication, cutting, edge-treatment or attachment requirements that should guide the proposed configurations? |
| A. | 1.There are no maximums at this time. Space and weight are a premium on the ship so keeping those manageable will be a benefit, but the focus ins on the fire protection performance.
2. The difficulty and complexity of shipbuilder modification and installation will be a decision factor. Highly specialized requirements will increase shipbuilder costs and affect commercialization. |
|
| 10/19/26 | Q. | Is the Navy open to multiple solutions addressing different shipbuilding scenarios, including coatings applied to existing joiner bulkheads, replacement panels, and integrated fire-resistant panels for new construction? |
| A. | The preference would be for a single solution that can address multiple scenarios, including new construction and retrofit (minimizing impact to existing layout) to avoid the need to test and qualify multiple solutions in a single project. | |
| 10/19/26 | Q. | Is the primary objective to bring currently non-AN-30-rated joiner bulkheads into AN-30 compliance, or is the Navy seeking improved fire containment beyond the existing performance level, with AN-30 serving as the minimum qualification requirement? |
| A. | The Navy is seeking joiner bulkheads that meet AN-30 classification. A greater level of fire protection can be proposed but not if it detrimentally increases thickness, weight, cost, etc. | |
| 11/2/26 | Q. | What types of joiner bulkheads are currently used in the applications targeted by this topic, and what are their existing fire-resistance classifications, if any? Is there a representative panel construction, thickness, weight or specification that the Navy recommends using as the baseline for Phase I? |
| A. | A. Current joiner bulkheads do not have a fire-resistance classification. Current panels are approximately 5/8” in thick with an areal weight of 1.2 – 3.1 lbs. and the following mechanical properties (based on 4 ft. X 7 ft. Panel)
|
** TOPIC NOTICE ** |
The Navy Topic above is an "unofficial" copy from the Navy Topics in the DoW FY-27 Release 1 SBIR BAA. Please see the official DoW Topic website at www.dodsbirsttr.mil/submissions/solicitation-documents/active-solicitations for any updates. The DoW issued its Navy FY-27 Release 1 SBIR Topics pre-release on October 7, 2026 which opens to receive proposals on October 28, 2026, and closes November 25, 202 (12:00pm ET). Direct Contact with Topic Authors: During the pre-release period (October 7, through October 27, 2026) proposing firms have an opportunity to directly contact the Technical Point of Contact (TPOC) to ask technical questions about the specific BAA topic. The TPOC contact information is listed in each topic description. Once DoW begins accepting proposals on October 28, 2026 no further direct contact between proposers and topic authors is allowed unless the Topic Author is responding to a question submitted during the Pre-release period. DoD On-line Q&A System: After the pre-release period, until November 11, 2026, at 12:00 PM ET, proposers may submit written questions through the DoW On-line Topic Q&A at https://www.dodsbirsttr.mil/submissions/login/ by logging in and following instructions. In the Topic Q&A system, the questioner and respondent remain anonymous but all questions and answers are posted for general viewing.